Calculates the schedule of the current project’s entire project family and stores the results in the current document. This command is available if the current project is part of a project family.
MacProject II first finds the master project for the whole project family and then goes through the subprojects, analyzing each one. If the current project is linked to more than one master project, MacProject II considers the current project to be the master for the whole family.
-- part contents for background part 7
----- text -----
If an ancestor of the current project is linked to more than one master, MacProject II considers that ancestor to be the master project.
You can cancel consolidation while it is in progress by pressing Command-period. Your calculation will be incomplete if you interrupt it, though. You should reconsolidate before saving, revert to the previously saved version, or don’t save the incomplete version at all.